Federal Court of Justice admits appeal on points of law relating to delivery of COVID-19 protective masks

Federal Court of Justice admits appeal on points of law relating to delivery of COVID-19 protective masks

Ausgabejahr 2025
Erscheinungsdatum 18.02.2026

Nr. 183/2025

Decisions of 7 October 2025 – VIII ZR 131/24 and VIII ZR 152/24

The Eighth Civil Panel of the Federal Court of Justice, which has jurisdiction for, among other matters, the law on the sale of goods, today issued its decision in two selected cases (VIII ZR 131/24 and VIII ZR 152/24) relating to the delivery of protective masks at the start of the COVID-19 pandemic and admitted the appeal on points of law (Revision) following the Federal Republic of Germany’s complaints against the denial of leave to appeal (Nichtzulassungsbeschwerden).

Facts and circumstances

In March/April 2020, the Federal Republic of Germany (the plaintiff in case VIII ZR 131/24 and the defendant in case VIII ZR 152/24), conducted an open house procedure for the swift procurement of, among other things, FFP2 and surgical masks. In such procedures, which are not subject to statutory provisions on the law of procurement, a public contracting authority concludes framework agreements for the procurement of goods under the terms of which any interested supplier may submit a bid on terms which have been predefined by the contracting authority. The bid is then “accepted”.

In late March 2020, the Federal Republic of Germany, represented by the Federal Ministry of Health (“contracting authority”), published a contract notice for the delivery of FFP2 and surgical masks and protective gowns. The contract notice stated, among other things, that the contract system relating to the conclusion of contracts for the delivery of personal protective equipment (PPE) was to commence with immediate effect and was to end at midnight on 30 April 2020. The latest possible delivery date was cited as 30 April 2020, within the normal business hours of a logistics company commissioned by the contracting authority and to which each delivery had to be made. All suppliers were to be able to apply to join the contract system at any time throughout the entire contract period by submitting a bid which had to encompass at least one of the aforementioned product groups and at least 250,000 units in each case.

The bid form, eligibility requirements, contract form relating to the delivery of PPE and tender specifications, among other documents, were all available to download via a link provided in the contract notice. The tender specifications, which formed part of the supply contract, stipulated a price of 4.50 euros net per FFP2 mask and 0.60 euros net per surgical mask. The contract form included the following clause:

3.2 The products shall be delivered to … [the logistics company] … ; the Supplier must contact … [the logistics company] to enquire about its usual business hours. Delivery to … [the logistics company] must be announced in text form at least three calendar days prior to the delivery date. The latest possible delivery date shall be 30 April 2020, within the business hours as referred to in sentence 1. In the case of non-compliance with the latest possible delivery date, the Contracting Parties’ reciprocal obligations shall lapse; delayed delivery shall not represent performance of the contract on the part of the Supplier (absolute fixed-date transaction).

The companies involved in the proceedings on the complaint against the denial of leave to appeal all submitted their bids for the delivery of FFP2 and surgical masks on time and their bids were all “accepted”.

In late April 2020, the contracting authority then noted that owing to the large number of parties participating in the open house procedure it would not be possible to accept all the deliveries on 30 April 2020. Those suppliers (including the companies participating in the appeal proceedings) which had notified that deliveries would be made and were possible on 30 April 2020 were given delivery slots on a later date.

On the dates communicated, the supplier in case VIII ZR 131/24 delivered the agreed quantity of 1.8 million FFP2 masks and the supplier in case VIII ZR 152/24 only delivered 340,000 FFP2 masks rather than the agreed quantity of 15 million FFP2 masks and 10 million surgical masks.

In case VIII ZR 131/24 the Federal Republic of Germany declared – without specifying a period of time for performance or cure – its partial rescission from the contract on the grounds that the supplied masks had been faulty. In case VIII ZR 152/24 the Federal Republic of Germany gave notice – also without specifying a period of time for performance or cure – of its rescission from the contract as regards the outstanding part of the delivery. Reference was made to the fact that delivery was not made in the contractually agreed quantity and to the nature of the contract as a fixed-date transaction.

Previous proceedings

In case VIII ZR 131/24 the Federal Republic of Germany submitted, among other things, that the purchase price paid to the supplier had been (partially) repaid. The majority of the action was unsuccessful in the lower courts.

In case VIII ZR 152/24 the supplier sought, among other things, payment of the remainder of the purchase price. The action was mostly successful in the lower courts.

In the opinion of the court of appeal, the Federal Republic of Germany had in both cases not effectively rescinded the respective sales contracts as required under section 323 (1) of the German Civil Code (Bürgerliches Gesetzbuch) because no time period had first been specified for cure. It was, therefore, not entitled to partial repayment of the purchase price paid (case VIII ZR 131/24) and was obligated to pay the (remainder of the) purchase price (case VIII ZR 152/24).

Specifying such a period of time in the delivery contract could have been dispensed with under the provision relating to an absolute/relative fixed-date transaction included in the supply contract which had been predefined by the Federal Republic of Germany. However, the relevant contract clause represented a standard business term and was ineffective in this instance. Fully exempting the user of a clause (in this case the Federal Republic of Germany) from the need to specify a period of time unreasonably disadvantaged the contracting party (section 307 (1) and (2) no. 1 of the German Civil Code) and was, therefore, likewise ineffective in commercial dealings – given the special circumstances which at any rate exist in this instance.

The contracting parties had also not agreed on a relative fixed-date transaction outside the contract clauses in which the specification of a period of time could have been dispensed with (section 323 (2) no. 2 of the German Civil Code) and in which case (if further conditions had been met) immediate withdrawal from the sales contract would have been possible. In particular, the Federal Republic of Germany was not able to successfully rely on the overall circumstances, especially the need to swiftly purchase the masks given the unfolding pandemic. In view of the pandemic – which both parties likewise noted was still unfolding and would not be concluded in the near term – it did have a discernible interest in swiftly concluding the contracts. However, at that time it could not have been assumed that, in the event of a (possibly only minimally) partial delivery, defective delivery or non-delivery of protective masks, the Federal Republic of Germany would no longer be interested in a delivery being made. Ultimately, the fact that deliveries had been postponed, on its own instigation, until after 30 April 2020 was proof thereof.

In both cases the court of appeal did not admit the appeals on points of law. The Federal Republic of Germany and, in case VIII ZR 131/24, also one of the suppliers filed complaints against the denial of leave to appeal against that decision.

The Federal Court of Justice’s ruling

On account of the fundamental importance of these cases, the Panel admitted the appeal on points of law following the Federal Republic of Germany’s complaints against the denial of leave to appeal.

The appeal on points of law in case VIII ZR 131/24 was only partially admitted. The Federal Republic of Germany’s application, in the alternative, for the subsequent delivery of (fault-free) protective masks, which was unsuccessful before the court of appeal, is excluded therefrom. The Panel also dismissed the complaint against the denial of leave to appeal filed by the supplier in this case. In each instance there was no ground to admit the appeal on points of law.

The Panel will hold an oral hearing on the appeals on points of law following receipt of the written grounds for the appeals on points of law and responses thereto.

Lower courts

VIII ZR 131/24
Bonn Regional Court – Judgment of 12 July 2023 – 20 O 49/22
Cologne Higher Regional Court – Judgment of 21 June 2024 – 6 U 112/23

and

VIII ZR 152/24
Bonn Regional Court – Judgment of 28 June 2023 – 1 O 221/22
Cologne Higher Regional Court – Judgment of 19 July 2024 – 6 U 101/23

Relevant legal provisions

German Civil Code

Section 307
Test of reasonableness of contents

(1) Provisions in standard business terms are ineffective if, contrary to the requirement of good faith, they unreasonably disadvantage the party contracting with the user. An unreasonable disadvantage also may arise from the provision not being clear and comprehensible.
(2) In case of doubt, an unreasonable disadvantage is to be assumed to exist if a provision
1. is not compatible with essential principles of the statutory provision from which it deviates, or
2. limits essential rights or duties inherent in the nature of the contract to such an extent that attainment of the purpose of the contract is jeopardised.
[…]

Section 323
Rescission for non-performance or for performance not as contractually agreed

(1) If, in the case of a reciprocal contract, the obligor does not render an act of performance which is due, or does not render it as contractually agreed, then the obligee may rescind the contract, provided the obligee has specified, without result, an additional period of time for performance or cure.
(2) Specifying a period of time may be dispensed with if
1. the obligor seriously and definitively refuses performance,
2. the obligor does not render performance by a date specified in the contract or within a period of time specified in the contract, in spite of the fact that, according to a notice given by the obligee to the obligor prior to conclusion of the contract or based on other circumstances attending at the time of its conclusion, the performance as per the date specified or within the period of time specified is of essential importance to the obligee, or
3. in the case of work not having been carried out as contractually agreed, special circumstances exist that, having weighed the interests of both parties against each other, justify immediate rescission.
[…]

Karlsruhe, 7 October 2025